Construction schedule dates and critical path

Reads and writes a project schedule, and works out each task's earliest and latest dates, its float and the critical path.

How the precision is kept

Dates are whole day numbers since 1970-01-01 UTC and every duration, lag and float is a whole number of days, so the critical path arithmetic is integer addition, subtraction, minimum and maximum with no rounding. The one conversion is on import, where a lag given in tenths of a minute is rounded to whole days.

Calculations under this policy

5 calculations in 1 source file. The code is read from the released app when this page loads. It is the calculation people run, not a copy kept for this page.

schedule-io.js BimCraft 0.8.1 64-bit 5 calculations Reviewed

Tests tools/bimcraft-test/schedule-test.mjs

Task duration

Exact

A task's duration in days, counting its start and finish day.

duration = finish − start + 1

Whole-number arithmetic on day numbers.

  • schedule-io.js
  • line 29
  • BimCraft 0.8.1
const dur = (t) => t.finish - t.start + 1;

Date read from a project file

Exact

Turns a date and time from a project XML file into a day number.

day = date part of the text

Only the first 10 characters are read, so the time of day is dropped: a task that finishes at 08:00 counts that whole day.

  • schedule-io.js
  • lines 59 to 60
  • BimCraft 0.8.1
/** "2026-11-02T08:00:00" → day number (the date part only; the file's clock times do not matter to a day plan). */
const dayOf = (s) => parseDay(String(s).slice(0, 10));

Link lag read from a project file

64-bit

Converts a dependency's lag from tenths of a minute to whole days.

lag (days) = Math.round(LinkLag ÷ 10 ÷ minutes per day)

The lag is rounded to the nearest whole day, so a lag of less than half a working day becomes 0. The file's LinkLagFormat is read and not used, so an elapsed-time lag is converted at the working-day length too.

  • schedule-io.js
  • lines 84 to 87
  • BimCraft 0.8.1
const lagMin = (+val(p, 'LinkLag') || 0) / 10;
void fmt;
if (!(ty >= 0 && ty <= 3) || !val(p, 'PredecessorUID')) { errors.push({ line: 0, message: 'link', task: name }); continue; }
preds.push({ uid: val(p, 'PredecessorUID'), type: TYPES[ty], lag: Math.round(lagMin / perDay) });

Early and late dates, float and the critical path

Exact

Each task's earliest start and finish, latest start and finish, float, and whether it is critical.

ES = max(own start, ES_pred + d); EF = ES + dur − 1; LS = min(finish − dur + 1, LS_succ − d); float = LS − ES

Only whole-number addition, subtraction, minimum and maximum, so a float of exactly 0 is a reliable test for a critical task. A task never starts before its own given start.

  • schedule-io.js
  • lines 212 to 224
  • BimCraft 0.8.1
for (const t of order) {
  t.es = t.start;                                                    // a task may not start before its own Start (it is the constraint)
  for (const e of inn.get(t)) t.es = Math.max(t.es, e.from.es + e.d);
  t.ef = t.es + dur(t) - 1;
}
const finish = list.length ? Math.max(...list.map((t) => t.ef)) : null;
for (const t of [...order].reverse()) {
  t.ls = finish - dur(t) + 1;
  for (const e of out.get(t)) t.ls = Math.min(t.ls, e.to.ls - e.d);
  t.lf = t.ls + dur(t) - 1;
  t.float = t.ls - t.es;
  t.critical = t.float === 0;
}

In detail

Method
Critical path method on calendar days. Each link is one inequality start(successor) ≥ start(predecessor) + d, with d from the link type and lag. Forward pass in topological order, then a backward pass from the latest finish.
Number types
Whole numbers held in 64-bit numbers. Durations count both the start and the finish day.
Limits
Only the date part of a start or finish is read; clock times are dropped. A lag is rounded to whole days at 480 minutes a day unless the file says otherwise, and the file's lag format field is not used. Every calendar day counts as a working day.

Approach: Exact values

Constants and factors are held as exact fractions from their definitions. The arithmetic is ordered so that no rounded factor is ever used.