Play a construction schedule on the model

Open a task list as a CSV, link each task to elements by a property, and move through the dates to see what is built, in progress and not started yet.

Written for BimCraft 0.11. The same help is inside the app: press F1.

What you'll do

Watch the building go up: each task in your schedule linked to the elements it builds, shown day by day.

Steps

  1. Open an IFC model and open 4D schedule in the left panel.
  2. Click Download a template for a task list with a week per storey, and change it in a spreadsheet. Or write your own.
  3. Click Open a task list… and choose the CSV.
  4. Drag the date slider, or click Play.
Step 1: the 4D schedule section open in the left panel, with the Open a task list button and the Download a template link
Step 1: the 4D schedule section open in the left panel, with the Open a task list button and the Download a template link
Step 2: the status line saying a task list was opened: house-schedule.csv with 4 tasks
Step 2: the status line saying a task list was opened: house-schedule.csv with 4 tasks
Step 3: the date slider moved to 2026-11-15, with the counts under it showing 1 built, 13 in progress and 29 not started, and the model drawn in ochre where work is under way
Step 3: the date slider moved to 2026-11-15, with the counts under it showing 1 built, 13 in progress and 29 not started, and the model drawn in ochre where work is under way
Step 4: the Play button, now reading Pause, above the Built, In progress and Not started counts, while the date moves on
Step 4: the Play button, now reading Pause, above the Built, In progress and Not started counts, while the date moves on

The task list

A CSV with a header row and the columns Task, Start, Finish, Field and Value. Commas or semicolons both work.

TaskStartFinishFieldValue
Level 12026-11-022026-11-13StoreyLevel 1
Roof2026-11-162026-11-20ClassIfcRoof
Roof2026-11-162026-11-20Pset_WallCommon.IsExternalYes
  • Write dates as YYYY-MM-DD.
  • A row links the task to every element whose Field has exactly that Value. The field is a property such as Storey, Class, Name, Type, Material, Tag or GlobalId, or any property written as its set and name: Pset_WallCommon.FireRating.
  • Repeat a task on more rows, with the same dates, to link more elements to it.

Stages and work packages

Add a Stage column, a Package column, or both, to gather tasks into stages and work packages. Phase and WBS work as column names too.

TaskStartFinishFieldValueStagePackage
Level 1 slab2026-11-022026-11-04ClassIfcSlabStructureFrame
Level 1 walls2026-11-052026-11-13StoreyLevel 1StructureFrame
Doors2026-11-302026-12-04ClassIfcDoorFit-outJoinery
  • A task belongs to one stage and one package. If a later row of the same task names another, that row is listed with its line number and left out.
  • The same package name in two stages is two packages.

When the list has groups, a Show list appears above the date. Choose a stage or a package and it plays as one:

  • the slider and Play run from the group's first start to its last finish,
  • only the group's tasks are listed and painted, and everything outside the group is see-through,
  • the line under the list says how many of its tasks are done, under way and to come on that date,
  • Select its elements selects every element of the group, for Show, Section or a schedule.

Choose Every task to see the whole schedule again.

What you should see

  • Built: elements whose tasks are all finished, in their own colors.
  • In progress: elements with a task under way that day, in ochre. A task is under way from its start date through its finish date.
  • Not started: see-through.
  • Elements in no task stay as they are. The list shows how many elements each task found. Rows that could not be read, or found nothing, are listed with their line numbers.
  • Open a Microsoft Project XML file (.xml) or a CSV that has a Predecessors column. Links can be finish to start, start to start, finish to finish or start to finish, each with a lead or lag in days.
  • Under the task list, the Gantt chart draws every task as a bar with arrows for the links. Tasks on the critical path are red. A link loop or a predecessor that does not exist is listed in the panel.
  • Save as MS Project XML and Save CSV with links write the schedule back with its links.