Tutorials BimCraft help Walkthroughs
Route ducts, drains, water and refrigerant pipes automatically
In the clash check, BimCraft finds a way round the open model for ducts, drainage by gravity, cold and hot water, and split or multi-split refrigerant pipes, and draws the runs with their fittings in one undo step. A drafting aid: sizes, slopes and checks come from the tables in the program and the numbers you type; nothing here says a design meets a code.
Written for BimCraft 0.11. The same help is inside the app: press F1.
What you'll do
Let BimCraft lay out a network of runs between connectors that already sit in the model, round walls and beams, then check it against numbers you can see.
Steps
- Open the model and the clash check. Under Route ducts automatically pick an air handler and its terminals, or under Route other systems automatically pick a system.
- Sanitary drainage by gravity. Type the outlet position and, if you have them, the stack positions. Tick Route every storey in one go to take every storey that has fixtures: each storey's drains meet the stack at their own level, and the stack runs from above the highest tap to its foot. Press Route.
- Trap to vent. The panel lists the distance from each trap to its vent. Type the most your code allows in Most from a trap to its vent; any fixture over it is listed as not done, with the millimetres over. Tick Vent through the stack when the fixtures have no vent stub of their own: the distance is then measured to the stack. BimCraft does not ship a code table for this: you type the number.
- Cold and hot water. Pick the source, type the pressure at the source and the pressure you need at a fixture. Tick Hot water, pick the heater's hot connection, and tick Return loop to end a return line at the heater's hot-return connection, or at any other connection you pick (that one ends 150 mm short, open, for you to join).
- Split, multi-split and VRF. Pick the outdoor unit, tick the indoor units and type each one's capacity. Type the limits from your maker's data. Type the equivalent length of a bend and of a branch kit (the maker's values) and the longest and total lengths are checked on equivalent lengths.
- Press Route. The panel says how many runs it drew, and anything it could not do and why. Undo takes everything back in one step.
What you should see
Pipes with elbows, tees and reducers; drains that fall at least the smallest slope for their size; vent stubs at the fixtures; refrigerant lines as a liquid and gas pair that turns the same way round every corner, with a branch kit marked where a branch leaves the trunk.
Good to know
- Where a drain meets another drain the model draws a tee. The plan names those places as 45-degree wye junctions so you can change the fitting.
- Hot water uses the fixture's own hot connection when its family has one, and a connection 100 mm beside the cold one when it does not.
- The refrigerant lines start between the two ports of each unit. When a unit's two ports stand too close for a bend, the pair stays centred between them.
- The water network uses the demand curve and friction numbers shown in the calculations; replace them with your code's before relying on the pressures.
- Large houses can take half a minute or more, mostly the hot network.
- This is a drafting aid. A qualified person checks sizes, slopes, vents and pressures against the code that applies.
Next
Check for clashes · Check pipes and ducts against the structure · Connections between pipes and equipment